Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | RIMA Fuel Switch in Bocaiúva (0889) |
---|---|
DOE that requested for issuance and date of request | SGS (19 Mar 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The baseline fuel oil consumption has been calculated on assumption that the same energy input would have been required in the baseline to produce the project output from the dolomite kiln. The DOE shall clarify how it has verified that this assumption is appropriate. | |
Date | 15 Apr 09 |