01:30 27 Dec 24
Project:
0809 Garganta da Jararaca Small Hydroelectric Power Plant (SHP)
- Issuance Request
Project | 0809: Garganta da Jararaca Small Hydroelectric Power Plant (SHP) |
---|---|
ISSUANCE STATUS | Issued (on 12 Dec 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 11 - 31 Dec 11 |
Monitoring report | Monitoring report (528 KB) |
Request for issuance | Signed form (79 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
51,183
Serial Range:
Block start: BR-5-76388017-1-1-0-809
Block end: BR-5-76439199-1-1-0-809
|
Verification and certification reports |
VVS/VVM version:
VVS 2.0
Certification report (148 KB) Verification report (640 KB) |
Additional documents |
GJ_CER_2012.07.03_v.03.xls (89 KB)
GJ_MR_2012 09 05_v 03.1.pdf (872 KB) |
Offset now: visit the United Nations Carbon Offset Platform