11:58 12 Mar 25
Project:
0809 Garganta da Jararaca Small Hydroelectric Power Plant (SHP)
- Issuance Request
Project | 0809: Garganta da Jararaca Small Hydroelectric Power Plant (SHP) |
---|---|
ISSUANCE STATUS | Issued (on 13 Jan 11) |
Monitoring period | 01 Dec 08 - 31 Dec 09 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
60,613
Serial Range:
Block start: BR-5-47321489-1-1-0-809
Block end: BR-5-47382101-1-1-0-809
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() ![]() ![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: