19:03 01 Feb 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Braço Norte III Small Hydro Plant (0667) |
---|---|
DOE that requested for issuance and date of request | SGS (17 Jul 08) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
OTHER ISSUES:
The PDD requires the calibration of the energy meter in accordance with national regulatory specifications and the previous verification report states that the energy meters are annually calibrated by the CEMAT transmission company. However, in this verification report, the DOE verified the calibration certificates which were issued on 13/12/2006. Further clarification is required on how the DOE has verified that the calibration is still valid up to 30/04/2008. |
|
Date | 20 Aug 08 |
Offset now: visit the United Nations Carbon Offset Platform