Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Repowering Small Hydro Plants (SHP) in the State of São Paulo, Brazil (0489) |
---|---|
DOE that requested for issuance and date of request | BVI (05 Mar 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
Discrepancies relating to the capacity of the plant exist in different documents: the monitoring report (p.3) mentions that the final capacity of Sao Joaquim is 8.37 MW and the verification report (p.11) states 8.64 MW while the PDD states that the final capacity is 8.05 MW after the expansion. During the second monitoring period, the DOE has verified that the added capacity to this plant was 2.5 MW as per the PDD. Further clarification is required on how the DOE verified the final capacity of the plants as per the PDD. | |
Date | 01 Apr 09 |