Project: 8793 Xinjiang Fuyun Tianrun Qiakuertu Phase I 49.5MW Wind Power Project - Issuance Request
Project 8793: Xinjiang Fuyun Tianrun Qiakuertu Phase I 49.5MW Wind Power Project
 
ISSUANCE STATUS Issued (on 23 Dec 16)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 13 - 31 Jul 16
Monitoring report Monitoring report (466 KB)
 
Request for issuance Signed form (329 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 290,861
Serial Range: Block start: CN-5-1022566297-2-2-0-8793     Block end: CN-5-1022857157-2-2-0-8793
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (834 KB)
Verification report (834 KB)
Additional documents ER (64 KB)
MR (485 KB)