Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 8282 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | 9MW Pure Low Temperature Waste Heat Recovery and Utilisation for Power Generation Project of Linxiang Conch Cement Company Limited |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) ACM0012 version 04 states that fcap is the ratio of maximum energy that could be recovered (MER) by the waste heat recovery equipment implemented under the CDM project activity and the actual energy recovered under the project activity (using direct measurement).The MER is a function of the maximum recoverable energy based on the operational time of the heat recovery equipment . The FSR states that the heat recovery equipment will be operational for 280 days/year .The DOE is requested to clarify why QOE,BL has been calculated based on 320 days of operation of the clinker line rather than the heat recovery equipment operational days of 280 days/year. Please refer to Page 32 of ACM0012 ,version 04.. | |
Date | 27 Jan 13 |