Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 6567 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Fuel Switch at Corobrik’s Driefontein Brick Factory in South Africa |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) The DOE shall validate how the project activity is in compliance with the applicability condition 8 of the methodology (paragraph 8 of AMS-III.B version 15) considering that 1) the energy content of the output (Qpj) seems being derived from the amount of fuel consumption (FC) multiplied by its net caloric value (Qpj=FC*NCV *1000/conversion factor from GJ to MWh) according to PDD page 30; and 2) the DOE clearly concluded in CAR B15 that "Qpj is not a directly monitored parameter but calculated". Please refer to VVM v1.2 paragraph 76.. 2) The DOE is requested to further validate how the project activity meets the requirements of paragraph 23 (a) of AMS-III.B version 15; in particular, given that the “output of element process i after the project activity has been implemented (QPJ,y)” will be calculated based on the natural gas consumption and its NCV rather than directly measured as required by the methodology. In doing so, the DOE should also explain how the monitoring plan will ensure that all the claimed emission reductions are due to the fuel switching measure and not on account of any other measures (such as increase in efficiency, etc). In addition, the DOE shall also explain the purpose of monitoring the temperature in the zones of the brick kiln considering monitoring temperature is not a requirement in the methodology. Please refer to VVM v1.2 paragraph 124(b).. |
|
Date | 04 Jan 13 |