21:30 09 Aug 26
Project:
5525 Gansu Yongdeng Longlin Hydro Power Project
- Issuance Request
| Project | 5525: Gansu Yongdeng Longlin Hydro Power Project |
|---|---|
| ISSUANCE STATUS | Withdrawn (on 16 Feb 23) |
| Monitoring period | 11 Jan 12 - 31 Dec 12 |
| Monitoring report |
Monitoring report (349 KB)
|
| Status of a monitoring report | The DOE has raised one or more corrective action requests or clarification requests, for which no response has been received from the project participant or the coordinating/managing entity |

Monitoring report
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: