CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 4988 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | El General Hydroelectric Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) The DOE shall further substantiate the suitability of the benchmark, in particular: (i) the inclusion of size risk premium given that it represents the risk profile of a particular type of project developer; (ii) the correctness of the benchmark determination; and (iii) why the data of US market has been used to determine the benchmark of a project activity implemented in Costa Rica. In doing so, please also provide the spreadsheet for benchmark calculation. Please refer to EB 39, Annex 10, sub-step 2b, paragraph (5); and VVM v.1.2 paragraph 111 (d).. 2) The DOE shall further substantiate the suitability of the project revenue, in particular: (i) the capacity payment, given that the calculated capacity payment (page 158 of the validation report) is 4.25 m USD which is not consistent with the applied value in the financial spreadsheet (4.088 m USD); and (ii) the energy payment, given that energy payment calculated as the product of the annual power output (196,210 MWh) and the electricity tariff (0.05 USD/kWh) is not consistent with the applied value in the financial spreadsheet (e,g, the 1st operation year, 9.637 m USD). Please refer to VVM v.1.2, paragraph 111 (a) & (b).. |
|
Date | 16 Feb 12 |