Project: 4800 San Clemente Hydroelectric Power Plant - Issuance Request
Project 4800: San Clemente Hydroelectric Power Plant
 
ISSUANCE STATUS Issued (on 04 Dec 15)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Nov 11 - 31 Dec 14
Monitoring report Monitoring report (538 KB)
 
Request for issuance Signed form (449 KB)
Amount of CERs CERs issued up to 31 December 2012: 10,461
CERs issued from 01 Jan 2013 until 31 December 2020: 17,639
Total amount of CERs: 28,100
Serial Range: Block start: CL-5-23219548-1-1-0-4800     Block end: CL-5-23230008-1-1-0-4800
Serial Range: Block start: CL-5-23230009-2-2-0-4800     Block end: CL-5-23247647-2-2-0-4800
Verification and certification reports VVS/VVM version: VVS 7.0
Certification report (618 KB)
Verification report (618 KB)
Additional documents PA4800 Monitoring Report MP1 (625 KB)
PA4800 Emission Reduction Calculation (2433 KB)