15:45 03 Nov 25
Project:
4800 San Clemente Hydroelectric Power Plant
- Issuance Request
| Project | 4800: San Clemente Hydroelectric Power Plant |
|---|---|
| ISSUANCE STATUS | Issued (on 24 Aug 22) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 15 - 31 Oct 18 |
| Monitoring report |
Monitoring report (420 KB)
|
| Request for issuance |
Signed form (165 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
30,889
Serial Range:
Block start: CL-5-39209596-2-2-0-4800
Block end: CL-5-39240484-2-2-0-4800
|
| Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
Certification report (404 KB)
Verification report (404 KB)
|
| Additional documents |
CDM MR San Clemente_v3 (415 KB)
Generation and ER San Clemente_v3 (40 KB)
|

Monitoring report
Generation and ER San Clemente_v3
Offset now: visit the United Nations Carbon Offset Platform