Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 4464 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | 10 MW Biomass Power Project in Amreli District, Gujarat, India |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1.The DOE is requested to further validate the investment barrier, in particular, the suitability of the 5% annual escalation applied to the biomass fuel cost, in line with the requirements of the VVM paragraphs 111 (b). 2.The DOE is requested to further validate the suitability of the prevailing practice barrier and barrier due to biomass fuel characteristics in line with the VVM 116 and 117, in particular, (a) how the selection of the Gujarat State has been considered suitable to demonstrate that the project activity is ¨first of its kind¨ considering that biomass utilization projects have been implemented in other states, in line with the requirements of EB35 Annex 34 paragraph 1 (d) and; (b) why the use of a more costly fuel in order to mitigate the barrier due to the biomass fuel characteristics cannot be translated into economical terms, in line with the requirements of EB50 Annex 13 paragraphs 7 and 8. 3.The monitoring of the electricity generated by the project (measured daily and aggregated monthly or measured monthly and aggregated annually) is not in line with the requirements of paragraph 17 of AMS-I.D. ver. 15 (as hourly measurement and monthly recording are required). |
|
Date | 26 Apr 11 |