Project: 4021 10 MW Tangka/Manipi Hydro Electric Power Plant - Issuance Request
Project 4021: 10 MW Tangka/Manipi Hydro Electric Power Plant
 
ISSUANCE STATUS Issued (on 06 Jul 15)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 14 - 31 Dec 14
Monitoring report Monitoring report (454 KB)
 
Request for issuance Signed form (41 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 31,380
Serial Range: Block start: ID-5-17215293-2-2-0-4021     Block end: ID-5-17246672-2-2-0-4021
Verification and certification reports VVS/VVM version: VVS 7.0
Certification report (46 KB)
Verification report (1179 KB)
Additional documents ER_Manipi 4th (30 KB)
MR_Manipi 4th (456 KB)