Project:
4021 10 MW Tangka/Manipi Hydro Electric Power Plant
- Issuance Request
| Project | 4021: 10 MW Tangka/Manipi Hydro Electric Power Plant |
|---|---|
| ISSUANCE STATUS | Issued (on 10 Jun 16) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 15 - 31 Dec 15 |
| Monitoring report |
Monitoring report (440 KB)
|
| Request for issuance |
Signed form (237 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
27,881
Serial Range:
Block start: ID-5-19622749-2-2-0-4021
Block end: ID-5-19650629-2-2-0-4021
|
| Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (434 KB)
Verification report (434 KB)
|
| Additional documents |
Final Monitoring Report (431 KB)
ER Spreadsheet (17 KB)
|

Monitoring report
ER Spreadsheet