16:27 23 May 25
Project:
3719 Sungai Kerling Hydropower Plant
- Issuance Request
Project | 3719: Sungai Kerling Hydropower Plant |
---|---|
ISSUANCE STATUS | Issued (on 28 Sep 17) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 15 - 04 Jan 17 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
11,245
Serial Range:
Block start: MY-5-12122410-2-2-0-3719
Block end: MY-5-12133654-2-2-0-3719
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
![]() ![]() |
Additional documents |
![]() ER_Sungai Kerling_MP4 (v1.2) (49 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: