3719 Sungai Kerling Hydropower Plant
- Issuance Request
| Project | 3719: Sungai Kerling Hydropower Plant |
|---|---|
| ISSUANCE STATUS | Issued (on 29 May 15) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 13 - 31 Dec 14 |
| Monitoring report |
Monitoring report (517 KB)
|
| Request for issuance |
Signed form (103 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
14,464
Serial Range:
Block start: MY-5-9844436-2-2-0-3719
Block end: MY-5-9858899-2-2-0-3719
|
| Verification and certification reports |
VVS/VVM version:
VVS 7.0
Certification report (332 KB)
Verification report (1261 KB)
|
| Additional documents |
Monitoring Report_Sungai Kerling_3rd (248 KB)
ER sheet_Sungai Kerling_3rd (50 KB)
|

Monitoring report
ER sheet_Sungai Kerling_3rd