15:25 11 Mar 26
Project:
3719 Sungai Kerling Hydropower Plant
- Issuance Request
| Project | 3719: Sungai Kerling Hydropower Plant |
|---|---|
| ISSUANCE STATUS | Issued (on 29 Jun 12) completeness check: complete | info & rep check: concluded |
| Monitoring period | 26 Jan 11 - 31 Dec 11 |
| Monitoring report |
Monitoring report (379 KB)
|
| Request for issuance |
Signed form (461 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
8,372
Serial Range:
Block start: MY-5-2932093-1-1-0-3719
Block end: MY-5-2940464-1-1-0-3719
|
| Verification and certification reports |
Certification report (251 KB)
Verification report (251 KB)
|
| Additional documents |
Monitoring report_version 1,5 (383 KB)
ER calculation_version 2,4 (44 KB)
|

Monitoring report
ER calculation_version 2,4
Offset now: visit the United Nations Carbon Offset Platform