15:59 23 May 25
Project:
3719 Sungai Kerling Hydropower Plant
- Issuance Request
Project | 3719: Sungai Kerling Hydropower Plant |
---|---|
ISSUANCE STATUS | Issued (on 29 Jun 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 26 Jan 11 - 31 Dec 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
8,372
Serial Range:
Block start: MY-5-2932093-1-1-0-3719
Block end: MY-5-2940464-1-1-0-3719
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: