19:16 27 Oct 25
Project:
3205 Sichuan Baoxing Dengchigou Second Level Hydropower Station
- Issuance Request
| Project | 3205: Sichuan Baoxing Dengchigou Second Level Hydropower Station |
|---|---|
| ISSUANCE STATUS | Issued (on 05 Sep 12) completeness check: complete | info & rep check: concluded |
| Monitoring period | 29 Nov 10 - 20 Apr 12 |
| Monitoring report |
Monitoring report (234 KB)
|
| Request for issuance |
Signed form (466 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
28,892
Serial Range:
Block start: CN-5-598978291-1-1-0-3205
Block end: CN-5-599007182-1-1-0-3205
|
| Verification and certification reports |
VVS/VVM version:
VVM 1.2
Certification report (115 KB)
Verification report (1254 KB)
|
| Additional documents |
Monitorin Report version2 for D (233 KB)
Final ERs for D (12 KB)
|

Monitoring report
Final ERs for D
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: