Project: 3205 Sichuan Baoxing Dengchigou Second Level Hydropower Station - Issuance Request
Project 3205: Sichuan Baoxing Dengchigou Second Level Hydropower Station
 
ISSUANCE STATUS Issued (on 05 Sep 12)   completeness check: complete | info & rep check: concluded
Monitoring period 29 Nov 10 - 20 Apr 12
Monitoring report Monitoring report (234 KB)
 
Request for issuance Signed form (466 KB)
Amount of CERs CERs issued up to 31 December 2012: 28,892
Serial Range: Block start: CN-5-598978291-1-1-0-3205     Block end: CN-5-599007182-1-1-0-3205
Verification and certification reports VVS/VVM version: VVM 1.2
Certification report (115 KB)
Verification report (1254 KB)
Additional documents Monitorin Report version2 for D (233 KB)
Final ERs for D (12 KB)