13:31 04 Jul 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3205 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Sichuan Baoxing Dengchigou Second Level Hydropower Station |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE should clarify how it has validated the reliability and credibility of the evidences related to the continuing and real actions taken to secure the CDM status of the project activity in parallel with its implementation, in particular, what specific CDM deliverables and/or actions were carried out under the 2nd and 3rd CDM consultancy cooperation agreements, dated February 2006 and April 2007, respectively, without which the gap between the project start date (18/11/2004) and the ERPA with the CER buyer (03/03/2008) would be more than 3 years, in line with para. 8 (b) and (c) of the EB 49, Annex 22 guidelines on the demonstration and assessment of the prior consideration of the CDM. 2. The DOE is requested to further substantiate how the proposed tariff for the project activity has been considered suitable as with the application of the highest tariff issued for similar projects in the province, published following EB 54, the IRR crosses the benchmark. When responding to this issue, the DOE is requested to refer to EB 53, Annex 32. |
|
Date | 13 Oct 10 |