22:26 01 Jul 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2862 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Sichuan Luding Moxi 20MW Hydropower Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to further explain how the proposed tariff for the project activity has been determined., as with the application of the highest tariff issued for similar projects in the province, the IRR crosses the benchmark. 2.The DOE shall further substantiate the common practice analysis, in particular, exclusion of two projects due to the lower investment costs and the other two due to lower operational hours compared to the other similar non-CDM projects as per the paragraph 118 (c) of VVM. |
|
Date | 02 Feb 10 |