07:37 14 Oct 25
Project:
2093 Huade Changshun 49.5MW Wind Power Project
- Crediting Period Renewal Request
[]
Project |
2093: Huade Changshun 49.5MW Wind Power Project
- ![]() PDD appendices ![]() ![]() - ![]() |
---|---|
Methodologies Used |
ACM0002 ver. 17 -
Grid-connected electricity generation from renewable sources
|
VVS Version | VVS 9.0 |
Standardized baselines used | N/A |
Amount of Reductions | 100,750 metric tonnes CO2 equivalent per annum |
Validation Opinion |
![]() |
Renewal Date |
10 Feb 17
(Renewable - Expired)
(view history)
completeness check: complete
info & rep check: concluded
Renewal no longer possible
|
Crediting Period (requested for renewal) |
24 Nov 16 - 23 Nov 23
Other crediting period(s): 24 Nov 09 - 23 Nov 16 |
Requests for Issuance
and related documentation |
|
Offset now: visit the United Nations Carbon Offset Platform