18:49 19 Sep 26
Project:
1980 Guangdong Shaoguan Yizhou Hydro Power Station
- Issuance Request
| Project | 1980: Guangdong Shaoguan Yizhou Hydro Power Station |
|---|---|
| ISSUANCE STATUS | Issued (on 16 Oct 12) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Nov 10 - 31 Mar 12 |
| Monitoring report |
Monitoring report (150 KB)
|
| Request for issuance |
Signed form (165 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
59,346
Serial Range:
Block start: CN-5-610496245-1-1-0-1980
Block end: CN-5-610555590-1-1-0-1980
|
| Verification and certification reports |
VVS/VVM version:
VVS 2.0
Certification report (225 KB)
Verification report (955 KB)
|
| Additional documents |
Guangdongyizhou-CER-2012.06.16 (37 KB)
Guangdongyizhou-MR-2012.06.16 (248 KB)
|

Monitoring report
Guangdongyizhou-CER-2012.06.16
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: