08:48 06 May 25
Project:
1831 Fujian Wuyishan Wenlin River 2nd and 3rd Level Hydropower Station
- Crediting Period Renewal Request
[]
Project |
1831: Fujian Wuyishan Wenlin River 2nd and 3rd Level Hydropower Station
- ![]() PDD appendices ![]() - ![]() |
---|---|
Methodologies Used |
AMS-I.D. ver. 18 -
Grid connected renewable electricity generation
|
VVS Version | VVS 9.0 |
Standardized baselines used | N/A |
Amount of Reductions | 16,272 metric tonnes CO2 equivalent per annum |
Validation Opinion |
![]() |
Renewal Date |
10 Jun 16
(Renewable - Expired)
(view history)
completeness check: complete
info & rep check: concluded
Renewal no longer possible
|
Crediting Period (requested for renewal) |
11 Dec 15 - 10 Dec 22
Other crediting period(s): 11 Dec 08 - 10 Dec 15 |
Requests for Issuance
and related documentation |
|
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: