23:33 09 Jul 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 1633 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | 28MW Jinkouba Hydropower Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. Further clarification is required on how the DOE has validated the suitability of the input values to the investment analysis, as per the guidance of EB 38 paragraph 54. 2. The DOE is requested to clarify how they have validated that the use of fixed input values (tariffs and O&M cost) in the IRR calculation is appropriate in the context of the project activity. 3. Further clarification is required why the tariff is not included in the sensitivity analysis and how the DOE has validated that an increase is unlikely to occur. 4. Further clarification is required on why the DOE has limited the common practice analysis to projects commissioned after 2000 and the capacity range of 20-250 MW. |
|
Date | 08 Sep 08 |