Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requested“8.75 MW Wind Power Project in Gujarat” (0776)
DOE that requested for issuance and date of requestTÜV NORD (14 Oct 08)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
The DOE is required to verify that the common meters at the substations measure electricity exported from WTGs belonging to this project activity only to ensure the pro-rata calculation approach is accurate to estimate emission reductions attributable to this project.
Date 31 Oct 08