Project:
0743 22.5 MW Bhilangana Hydro Power Project (BHPP)
- Issuance Request
Project | 0743: 22.5 MW Bhilangana Hydro Power Project (BHPP) |
---|---|
ISSUANCE STATUS | Issued (on 05 Apr 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 11 - 31 Dec 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
60,204
Serial Range:
Block start: IN-5-172102226-1-1-0-743
Block end: IN-5-172162429-1-1-0-743
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
![]() ![]() |
Additional documents |
![]() ![]() |