Registration Request for Review Form
|
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
|---|
| Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 5876 |
|---|---|
| Title of the proposed CDM project activity/PoA submitted for registration | Thai Sritong Biomass Energy |
| Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
| The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
The participation requirements as set out in paragraph 28 to 30 of the CDM modalities and procedures are satisfied; Comments by local stakeholders have been invited, a summary of the comments received has been provided, and a report to the designated operational entity (DOE) on how due account was taken of any comments has been received; Project Participants have submitted to the DOE documentation on the analysis of the environmental impacts of the project activity, including transboundary impacts and, if those impacts are considered significant by the project participants or the host Party, have undertaken an environmental impact assessment in accordance with procedures as required by the host Party; The project activity is expected to result in a reduction in anthropogenic emissions by sources of greenhouse gases that are additional to any that would occur in the absence of the proposed project activity, in accordance with paragraphs 43 to 52 of the CDM modalities and procedures; The baseline and monitoring methodologies comply with requirements pertaining to methodologies previously approved by the Executive Board; Provisions for monitoring, verification and reporting are in accordance with decision 17/CP.7, the CDM modalities and procedures and relevant decisions of the COP/MOP; The project activity conforms to all other requirements for CDM project activities in decision 17/CP.7, the CDM modalities and procedures and relevant decisions by the COP/MOP and the Executive Board. |
|
| The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
The DOE shall, prior to the submission of the validation report to the Executive Board, have received from the project participants written approval of voluntary participation from the designated national authority of each Party involved, including confirmation by the host Party that the project activity assists it in achieving sustainable development; In accordance with provisions on confidentiality contained in paragraph 27(h) of the CDM modalities and procedures, the DOE shall make publicly available the project design document; The DOE shall receive, within 30 days, comments on the validation requirements from Parties, stakeholders and UNFCCC accredited non-governmental organizations and make them publicly available; After the deadline for receipt of comments, the DOE shall make a determination as to whether, on the basis of the information provided and taking into account the comments received, the project activity should be validated; The DOE shall inform project participants of its determination on the validation of the project activity. Notification to the project participants will include confirmation of validation and the date of submission of the validation report to the Executive Board; The DOE shall submit to the Executive Board, if it determines the proposed project activity to be valid, a request for registration in the form of a validation report including of the project design document, the written approval of the host Party and an explanation of how it has taken due account of comments received. |
|
There are only minor issues which should be addressed by the DOE/project participants prior to the registration of the project. |
|
| Additional information | |
|
1) The project cost has been validated as the cost related to the purchase, construction, and installation of the whole biomass cogeneration system with 8 MW electrictiy generating capacity. The DOE is requested to justify the appropriateness of this total cost, considering that in the absence of the project activity, the project participant would have installed a biomass cogeneration system supplying heat and power for captive consumption (700 kW electricity generating capacity) which was validated as the baseline. Please refer to VVM paragraph 111 (a). 2) The validation report states that the fuel cost (for Empty Fruit Bunch (EFB) and shell) has been included, because in the absence of the project activity, the Project participants will sell the biomass, therefore it is an opportunity cost (Validation report, p. A-43). The DOE is requested to further justify the appropriateness of including the cost of EFB and shell in the IRR calculations considering these biomass are generated on-site from the CPO mill. Please refer to VVM paragraph 111 (a). 3) The cost of equity has been determined based on the Capital Asset Pricing Model (CAPM), where the market return (Rm) has been calculated on the basis of SET50 calculated from the prices of 50 selected SET stocks by the Stock Exchange of Thailand. The market return is 21%, calculated based on 2002-2008 data. The DOE is requested to justify the appropriateness of determining market return value based only on 2002-2008 data. Please refer to VVM paragraph 112. |
|
| Date | 04 Sep 12 |

The participation requirements as set out in paragraph 28 to 30 of the CDM modalities and procedures are satisfied;
The project activity is expected to result in a reduction in anthropogenic emissions by sources of greenhouse gases that are additional to any that would occur in the absence of the proposed project activity, in accordance with paragraphs 43 to 52 of the CDM modalities and procedures;