23:07 10 Feb 25
Project:
7529 Grid connected wind power project in Maharashtra, India by Bhilwara
- Issuance Request
Project | 7529: Grid connected wind power project in Maharashtra, India by Bhilwara |
---|---|
ISSUANCE STATUS | Issued (on 23 Jul 18) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 01 Mar 18 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
477,029
Serial Range:
Block start: IN-5-248448641-2-2-0-7529
Block end: IN-5-248925669-2-2-0-7529
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 1.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: