18:27 01 Aug 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 5154 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Shanxi Linfen 2×6MW Coke Oven Gas Power Generation Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) The DOE shall further substantiate the suitability of input values, in particular: (i) whether assumed steam price reflects the savings due to the avoided production cost of heat using the waste gas fired boilers in the pre-project scenario; (ii) the assumed steam price given that the two parties of the steam agreement are identical and it is not clear whether the steam of the other referred projects are similar and comparable to the steam of the proposed project activity; (iii) the assumed steam supply given that it is lower than the actual steam supply (112,000 tonnes); (iv) the assumed electricity tariff given that the tariff agreement between the coke plant and the power plant is deemed as an internal contract, in doing so please also explain how the DOE has validated that the tariff for large size industry users published by Shanxi Province Price Bureau (JinJiaShangZi170) is applicable to the project activity; (v) the total static investment given that it is not consistent with the value applied in the PDD during GSC and the DOE did not provide any justification on the inconsistency, in doing so, please also provide a breakdown of the total static investment; (vi) the assumed COG price considering that the project owner and the owner of the coke plant are identical. Please refer to paragraph 111(a) & (b) of VVM version 1.2 and paragraph 93 of EB 60.. 2) The DOE shall further explain how it has validated the correctness and accuracy of the investment analysis, in particular: (i) the recoverable value of the replaced existing heat generation system (including the two gas boiler) has not been considered into the investment analysis; (ii) the VAT is calculated on the gross revenue of the project activity. Please refer to paragraph 111 (a) & (d) of VVM version 1.2.. 3) The DOE shall further substantiate the compliance of the applied equations to calculate the baseline emissions, given that in the absence of the project activity the waste gas was partially used for heat generation and the project activity is to improve the recovery of the waste gas. Please refer to section 1.1.1 (page 14) and section 1.2 (page 22) of ACM0012 version 4.. |
|
Date | 21 Nov 12 |