Project:
5082 Lopburi Solar Power Plant Project
- Issuance Request
| Project | 5082: Lopburi Solar Power Plant Project |
|---|---|
| ISSUANCE STATUS | Issued (on 30 Jul 20) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 19 - 31 Dec 19 |
| Monitoring report |
Monitoring report (407 KB)
|
| Request for issuance |
Signed form (48 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
62,258
Serial Range:
Block start: TH-5-14643276-2-2-0-5082
Block end: TH-5-14705533-2-2-0-5082
|
| Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (604 KB)
Verification report (604 KB)
|
| Additional documents |
LSP MR07 (version 1.1) 2020.04.06 (484 KB)
LSP_ER calculation_MR07 (Version 1.1) 20200406 (156 KB)
|

Monitoring report
LSP_ER calculation_MR07 (Version 1.1) 20200406