19:08 03 May 25
Project:
4898 5.35 MW Wind Power Project by GeeCee Ventures Ltd
- Issuance Request
Project | 4898: 5.35 MW Wind Power Project by GeeCee Ventures Ltd |
---|---|
ISSUANCE STATUS | Issued (on 15 Dec 14) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jul 11 - 31 Jan 14 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
9,287
CERs issued from 01 Jan 2013 until 31 December 2020: 4,993 Total amount of CERs: 14,280
Serial Range:
Block start: IN-5-200486288-1-1-0-4898
Block end: IN-5-200495574-1-1-0-4898
Serial Range: Block start: IN-5-200495575-2-2-0-4898 Block end: IN-5-200500567-2-2-0-4898 |
Verification and certification reports |
VVS/VVM version:
VVS 7.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform