CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3162 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Tiantie Metallurgy Group CDQ Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to further explain how it has validated the investment analysis to be in line with VVM v1 paragraph 111 guidance, in particular: (i) the appropriateness of the tariff (0.42 RMB/kWh) used in the investment analysis and whether this tariff is more conservative than the electricity tariff the PP was paying to the grid company before the implementation of the proposed project activity; (ii) the applicability of the grid connection charges when, as indicated by the DOE, this grid charge was being paid to the grid company in the baseline scenario; (iii) the suitability of the O&M (20% of total investment according to validation report) cost and the inclusion of energy cost as part of O&M cost when the PP indicates in PDD page 21 that “waste gas/heat –fired power plants have very low operational costs (waste energy does not come at a cost for the facility)”; and (iv) estimated annual power generation and the 80% factor used in year one. 2. The DOE is requested to substantiate how it has validated the elimination of alternative P11 (existing power generating equipment is maintained and additional electricity generated by grid connected power plants) when this is a realistic baseline scenario as described in PDD. 3. The DOE should provide all the spreadsheets used for baseline calculation and emission reduction calculations. |
|
Date | 05 Jul 10 |