Project 2551: Xinjiang Kaiduhe River Chahan Wusu Hydropower Project
 
ISSUANCE STATUS Issued (on 27 Dec 12)   completeness check: complete | info & rep check: concluded
Monitoring period 28 Jun 12 - 27 Jul 12
Monitoring report Monitoring report (314 KB)
 
Request for issuance Signed form (89 KB)
Amount of CERs CERs issued up to 31 December 2012: 121,663
Serial Range: Block start: CN-5-694889653-1-1-0-2551     Block end: CN-5-695011315-1-1-0-2551
Verification and certification reports VVS/VVM version: VVS 2.0
Certification report (1078 KB)
Verification report (1078 KB)
Additional documents 2551 8 Monitoring Report (314 KB)
2551 8 CER Calculation (57 KB)