18:44 14 Jan 25
Project:
2475 LG Chem Naju plant fuel switching project
- Issuance Request
Project | 2475: LG Chem Naju plant fuel switching project |
---|---|
ISSUANCE STATUS | Issued (on 29 Aug 14) completeness check: complete | info & rep check: concluded |
Monitoring period | 04 Jun 09 - 23 Feb 11 |
Monitoring report | Monitoring report (350 KB) |
Request for issuance | Signed form (49 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
12,831
Serial Range:
Block start: KR-5-123548901-1-1-0-2475
Block end: KR-5-123561731-1-1-0-2475
|
Verification and certification reports |
VVS/VVM version:
VVS 6.0
Certification report (521 KB) Verification report (521 KB) |
Additional documents | MR_LG_Chem_ver3.2 (344 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: