2475 LG Chem Naju plant fuel switching project
- Issuance Request
Project | 2475: LG Chem Naju plant fuel switching project |
---|---|
ISSUANCE STATUS | Issued (on 29 Aug 14) completeness check: complete | info & rep check: concluded |
Monitoring period | 04 Jun 09 - 23 Feb 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
12,831
Serial Range:
Block start: KR-5-123548901-1-1-0-2475
Block end: KR-5-123561731-1-1-0-2475
|
Verification and certification reports |
VVS/VVM version:
VVS 6.0
![]() ![]() |
Additional documents |
![]() |