Project: 2532 Jiangsu Dongling Wind Farm Project - Issuance Request
Project 2532: Jiangsu Dongling Wind Farm Project
 
ISSUANCE STATUS Issued (on 10 Jun 21)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 13 - 09 Mar 17
Monitoring report Monitoring report (1440 KB)
 
Request for issuance Signed form (304 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 436,006
Serial Range: Block start: CN-5-1114972304-2-2-0-2532     Block end: CN-5-1115408309-2-2-0-2532
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (753 KB)
Verification report (753 KB)
Additional documents Untitled (uploaded 31 Dec 20 08:21:25) (100 KB)
Untitled (uploaded 31 Dec 20 08:39:24) (484 KB)