23:15 14 Jan 25
Project:
2366 Korea East-West Power Dangjin small hydro power plant project (5MW)
- Issuance Request
Project | 2366: Korea East-West Power Dangjin small hydro power plant project (5MW) |
---|---|
ISSUANCE STATUS | Issued (on 07 Mar 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 10 - 31 Mar 11 |
Monitoring report | Monitoring report (462 KB) |
Request for issuance | Signed form (51 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
17,424
Serial Range:
Block start: KR-5-104633075-1-1-0-2366
Block end: KR-5-104650498-1-1-0-2366
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
Certification report (749 KB) Verification report (749 KB) |
Additional documents |
Monitoring report_final (545 KB)
ER sheet (117 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: