21:14 10 Feb 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Hangyeong second phase SS-wind power Project (1000) |
---|---|
DOE that requested for issuance and date of request | KSA (19 Apr 11) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
1) There are inconsistencies with two different import figures shown on worksheets "Electricity Transmitted" and "Data&Parameters" with some instances in "Electricity Transmitted" showing net electricity supplied to the grid as higher than the electricity generated. Further clarification is required as to how the DOE verified the parameter "EGy net electricity supplied to the grid". 2) There was a gap of 6 months in the period covered by calibration. According to the EB52 Annex 60, a correction should be made to both the exported (-0.5%) and the imported (+0.5%) electricity. Clarification is required as to why the EB52 Annex 60 guidance has not been applied to the imported electricity. |
|
Date | 29 May 11 |