Project: 10398 Off-grid Solar PV project at IAMGOLD Essakane SA Gold Mine - Issuance Request
Project 10398: Off-grid Solar PV project at IAMGOLD Essakane SA Gold Mine
 
ISSUANCE STATUS Issued (on 19 Feb 20)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jun 18 - 31 May 19
Monitoring report Monitoring report (1864 KB)
Submission of comments to the DOE

The comment period is over.
 
Request for issuance Signed form (37 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 19,119
Serial Range: Block start: BF-5-44110-2-2-0-10398     Block end: BF-5-63228-2-2-0-10398
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (208 KB)
Verification report (208 KB)
Additional documents ER spreadsheet (49 KB)
Untitled (uploaded 04 Dec 19 14:39:20) (1127 KB)