9460 20 MW LNJP Wind Project Power Project, Rajasthan
- Issuance Request
Project | 9460: 20 MW LNJP Wind Project Power Project, Rajasthan |
---|---|
ISSUANCE STATUS | Issued (on 04 May 22) | info & rep check: concluded |
Monitoring period | 03 Sep 14 - 30 Sep 20 |
Monitoring report | Monitoring report (574 KB) |
Request for issuance | Signed form (63 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
140,584
Serial Range:
Block start: IN-5-291122616-2-2-0-9460
Block end: IN-5-291263199-2-2-0-9460
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (216 KB) Verification report (216 KB) |
Additional documents |
Untitled (uploaded 23 Feb 21 11:56:35) (328 KB)
Untitled (uploaded 23 Feb 21 11:56:35) (25 KB) |
Previous submissions
Submission date | Outcome |
---|---|
23 Feb 21 | CC complete | I&R concluded |