09:33 18 May 25
Project:
3651 Sichuan Longdong 30MW Hydropower Project of China
- Issuance Request
Project | 3651: Sichuan Longdong 30MW Hydropower Project of China |
---|---|
ISSUANCE STATUS | Issued (on 08 Mar 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 21 Dec 11 - 20 Aug 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
74,290
Serial Range:
Block start: CN-5-753567995-1-1-0-3651
Block end: CN-5-753642284-1-1-0-3651
|
Verification and certification reports |
VVS/VVM version:
VVS 2.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: