2539 Sichuan Jinxi Hydropower Project
- Issuance Request
Project | 2539: Sichuan Jinxi Hydropower Project |
---|---|
ISSUANCE STATUS | Issued (on 21 May 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 26 Apr 11 - 25 Aug 11 |
Monitoring report | Monitoring report (271 KB) |
Request for issuance | Signed form (337 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
280,061
Serial Range:
Block start: CN-5-557909396-1-1-0-2539
Block end: CN-5-558189456-1-1-0-2539
|
Verification and certification reports |
Certification report (113 KB)
Verification report (576 KB) |
Additional documents |
4th ER Calculation Spreadsheet of Jinxi (22 KB)
2539-Monitoring Report_4th (220 KB) Appendix1-Clarification for the surface area of reservoir about Jinxi hydropower station (682 KB) Appendix2-The evidenced about the high water flow from May to August (375 KB) Appendix3-The Preliminary Design Report of Jinxi Hydropower Project (654 KB) |