09:31 26 Apr 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2304 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | 73 MW Tonghua Iron & Steel Waste Gas and Heat Power Generation Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE shall validate the cessation of project implementation by means of credible evidence such as cancellation of contracts or revocation of government permits in accordance with EB 41 paragraph 67. 2. The DOE shall ensure that the project description clearly states the differences resulting from the project activity compared to the pre-project situation. 3. The PP/DOE should further substantiate on how they have validated the existence of: (a) barrier due to the prevailing practices, in particular, how the project activity and other power generation technologies in the steel making plants in China have been differentiated; and (b) technological barrier as it appears that installation of Steam Network Power Generation System does not provide any solutions to technical difficulties of the gas turbines. 4. The PP/DOE should further substantiate the applicability of ACM0012 version 02 to the project activity, in particular, (a) what would happen to the waste gas in the absence of the project activity; (b) whether the project activity is going to be built in an existing or new facility as forecasted generation of the BFG in 2009 is almost double than that in 2006; and (c) whether there is any on-site energy generation facility prior to implementation of the project activity. 5. The data used to calculate the grid emission factor in the PDD submitted for registration was not available at the commencement of validation (February 2008). The PP and DOE are therefore requested to amend the grid emission factor using data, which was available at this date and provide corresponding calculation of the emission reductions. |
|
Date | 05 Jun 09 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: