Project: 4941 Uganda Nile Basin Reforestation Project No 4 - Issuance Request
Project 4941: Uganda Nile Basin Reforestation Project No 4
 
ISSUANCE STATUS Issued (on 30 Dec 20)   completeness check | info & rep check: concluded
Monitoring period 01 Apr 08 - 31 Dec 17
Monitoring report Monitoring report (659 KB)
Submission of comments to the DOE

The comment period is over.
Status of a monitoring report The DOE has raised one or more corrective action requests or clarification requests, for which no response has been received from the project participant or the coordinating/managing entity
Requests for post-registration changes containing applicable deviations PRC-4941-001 - Approved
Requests for post-registration changes submitted with the issuance request PRC-4941-001
 
Request for issuance Signed form (251 KB)
Amount of CERs CERs issued up to 31 December 2012: 0
CERs issued from 01 Jan 2013 until 31 December 2020: 3,276
Total amount of CERs: 3,276
Serial Range: Block start: UG-6-9392751-2-2-1-4941     Block end: UG-6-9396026-2-2-1-4941
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (946 KB)
Verification report (946 KB)
Additional documents Uganda Nile Basin Reforestation Project No. 4_MR_20200721-clean (879 KB)
Rwoho_Revised Plantation schedule_Rev01_Project4 (26 KB)
UNBRP_Carbon calculation_Project4_20200716 (793 KB)

Previous submissions

Submission date Outcome
15 Jul 20
22 Jul 20 CC complete | I&R incomplete