Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 6548 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Gansu Jingyuan Coal Mine Group Jieneng Thermoelectricity Company CMM Power Generation Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) The DOE is requested to further justify the choice of benchmark of 15% equity IRR (post tax) for coal mining sector as it appears that the project participant, Baiyin Jieneng Thermoelectricity Co Ltd., appears to be purely an egergy generation company. In doing so, please clarify the core operation of Baiyin Jieneng Thermoelectricity Co Ltd. Please refer to VVM v 1.2 paragraph 112.. 2) The DOE is requested to further substantiate the investment analysis: a) Tax calculation, in particular, to clarify why various taxes (VAT, educational surcharge, urban maintenance and construction tax and income tax) have been accounted as costs in the cash outflow considering that the revenues are based on the avoided costs of electricity and coal. b) NCV of coal based on China Energy Statistical Yearbook, in particular, whether the value applied is conservative in comparison to the actual NCV of the type of the coal used in the baseline. c) the O&M cost, in particular, what Material purchasing cost of 1,007,500 RMB consists of and if it includes cost of CMM. Please refer to VVM v 1.2 paragraph 111.. 3) The DOE is requested to further substantiate how it has validated that all possible options that are technically feasible were included, for example, retrofitting of the existing system that operated with high concentration CMM between 2004 and February 2008 to operate with the new concentration. Please note that the list of options in the applied methodology are not exhaustive and possible options are not limited to those listed in page 6 of the methodology. Please refer to VVM v1.2 paragraph 83.. 4) The DOE is requested to further substantiate the elimination of scneario 4 Use for additional grid power generation, in particular, to justify how it has validated the discount rate of 15% (post tax equity IRR benchmark) for coal sector, considering that this alternative considers 100% export to the grid. Please refer to VVM version 1.2 paragraph 83.. 5) The DOE is requested to further substantiate how the electricity consumption by the project activity is monitored by clarifying how the monitoring plan ensures that all electricity consumption that results from the project activity are captured by monitoring the net electricity supply to the Jingyuan Coal Group's grid. Please refer to VVM version 1.2 paragraph 123 (a).. |
|