Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 4476 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Madushan Hydropower Project on Honghe River in Yunnan Province, China |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to clarify how it has validated the O&M cost as: a) it has validated the unit O&M costs as 0.06millionRMB/MW (validation report page 20) while in the spreadsheet, it is 0.156 million RMB/MW (44.94 million RMB/ 288 MW); and b) it is not clear if the projects used for comparison are suitable in the context of the project activity of 288 MW as the capacity of such projects are not clearly defined. In doing so, please refer to VVM version 1.2 paragraph 111. 2. The DOE is requested to clarify how it has validated the net power export to the grid as: a) it has validated the net electricity output of 1,314,432 MWh/year (4,564 MWh/MW x 228 MW, validation report page 19) while according to the project description, it is 1,217,569 MWh and in the spreadsheet, it is 1,164,249 MWh/year for the first three operational years and 1,217,569 MWh/year for the remaining years; and b) it is not clear how it has validated the suitability of applying: i) 95% coefficient of effective electricity; ii) 2% loss; and iii) 0.5% auxiliary consumption to be conservative. In doing so, please refer to VVM version 1.2 paragraph 111. |
|
Date | 08 May 11 |