Project: 3307 Pingtou 180MW Hydropower Project in Sichuan Province - Issuance Request
Project 3307: Pingtou 180MW Hydropower Project in Sichuan Province
 
ISSUANCE STATUS Issued (on 25 Jul 12)   completeness check: complete | info & rep check: concluded
Monitoring period 01 May 11 - 25 Aug 11
Monitoring report Monitoring report (135 KB)
 
Request for issuance Signed form (940 KB)
Amount of CERs CERs issued up to 31 December 2012: 142,385
Serial Range: Block start: CN-5-582217751-1-1-0-3307     Block end: CN-5-582360135-1-1-0-3307
Verification and certification reports VVS/VVM version: VVM 1.2
Certification report (60 KB)
Verification report (707 KB)
Additional documents 3307 1 Monitoring Report (392 KB)
3307 1 CER Calculation (40 KB)

Previous submissions

Submission date Outcome
15 Feb 12 CC complete | I&R incomplete
30 Mar 12 CC complete | I&R incomplete