18:20 03 Dec 24
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 10258 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Clinker Optimization in cement types production at Derba MIDROC cement plant |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
The participation requirements as set out in paragraph 28 to 30 of the CDM modalities and procedures are satisfied; Comments by local stakeholders have been invited, a summary of the comments received has been provided, and a report to the designated operational entity (DOE) on how due account was taken of any comments has been received; Project Participants have submitted to the DOE documentation on the analysis of the environmental impacts of the project activity, including transboundary impacts and, if those impacts are considered significant by the project participants or the host Party, have undertaken an environmental impact assessment in accordance with procedures as required by the host Party; The project activity is expected to result in a reduction in anthropogenic emissions by sources of greenhouse gases that are additional to any that would occur in the absence of the proposed project activity, in accordance with paragraphs 43 to 52 of the CDM modalities and procedures; The baseline and monitoring methodologies comply with requirements pertaining to methodologies previously approved by the Executive Board; Provisions for monitoring, verification and reporting are in accordance with decision 17/CP.7, the CDM modalities and procedures and relevant decisions of the COP/MOP; The project activity conforms to all other requirements for CDM project activities in decision 17/CP.7, the CDM modalities and procedures and relevant decisions by the COP/MOP and the Executive Board. |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
The DOE shall, prior to the submission of the validation report to the Executive Board, have received from the project participants written approval of voluntary participation from the designated national authority of each Party involved, including confirmation by the host Party that the project activity assists it in achieving sustainable development; In accordance with provisions on confidentiality contained in paragraph 27(h) of the CDM modalities and procedures, the DOE shall make publicly available the project design document; The DOE shall receive, within 30 days, comments on the validation requirements from Parties, stakeholders and UNFCCC accredited non-governmental organizations and make them publicly available; After the deadline for receipt of comments, the DOE shall make a determination as to whether, on the basis of the information provided and taking into account the comments received, the project activity should be validated; The DOE shall inform project participants of its determination on the validation of the project activity. Notification to the project participants will include confirmation of validation and the date of submission of the validation report to the Executive Board; The DOE shall submit to the Executive Board, if it determines the proposed project activity to be valid, a request for registration in the form of a validation report including of the project design document, the written approval of the host Party and an explanation of how it has taken due account of comments received. |
|
There are only minor issues which should be addressed by the DOE/project participants prior to the registration of the project. | |
Additional information | |
1) The DOE is requested to further explain how it was validated that the determination of the baseline benchmark values of share of clinker for the cement types PLC and PC was done in accordance to the applied methodology, (Step 2.1.), considering that the two mentioned types of blended cement have never been produced or used in the host country and the applied methodology only provides for the use of existing statistical data of mass fraction of clinker for each relevant cement type. In doing so, the DOE shall also explain why a request for deviation of the methodology was not submitted prior to the submission of a request for registration or publication of the PDD for global stakeholder consultation, in accordance with Para 49 and 50 of the PCP, Version 9, in order to address this issue. 2) The DOE is requested to confirm the correctness of the input data used by the PP to determine the baseline benchmark of share of clinker per tonne of BC for the cement type PPC. When comparing the current submitted data with the data provided at the first request for registration, inconsistent values were found applying to the “Annual historical production in 2008” of Mugher plant (662,278 tonnes in the current Request for Registration and 603,375 tonnes in the first Request for Registration). |
|
Date | 01 Jun 16 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: