01:18 29 Nov 23
Project:
7053 Ryesonggang Hydropower Plant No.5, DPR Korea
- Issuance Request
Project | 7053: Ryesonggang Hydropower Plant No.5, DPR Korea |
---|---|
ISSUANCE STATUS | Issued (on 23 Nov 17) completeness check: complete | info & rep check: concluded |
Monitoring period | 30 Nov 13 - 31 Mar 17 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
87,529
Serial Range:
Block start: KP-5-284621-2-2-0-7053
Block end: KP-5-372149-2-2-0-7053
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: