12:15 23 May 26
Project
6782 :
Pantabangan Hydro Electric Power Plant Refurbishment and Upgrade Project in Nueva Ecija, Philippines
| Project title |
Pantabangan Hydro Electric Power Plant Refurbishment and Upgrade Project in Nueva Ecija, Philippines
- project design document (3062 KB)
PDD appendices Appendix 1 - 6782- 5_Attachment_3A_Calculation_and_Comparison_of_Financial_Indicator_as_of_18June2012_cleaned_as_of_20july_1-NWIE5B_CC- 2012 07 23 (83 KB)
Appendix 2 - 6782- Attachment_3B_Calculation_of_Financial_Indicator_Actual_savings_cost_REV2_cleaned_20July_1-NWIE5D_CC- 2012 07 23 (84 KB)
Appendix 3 - 6782- Attachment 1 _ GEF 21Feb2012 -2012 07 23 (229 KB)
Appendix 4 - 6782- Attachment 2. Pantabangan Diesel For Genset_16 April 2012-2012 07 23 (68 KB)
Appendix 5 - 6782- Attachment 4 Feasibility Study Report_may2012- 2012 07 23 (922 KB)
Appendix 6 - 6782- Attachment 5. Additional Annual Generation_03May2012- 2012 07 23 (27 KB)
- registration request form (110 KB)
|
|---|---|
| SDC description report | Not Available. Please refer to our Further Information on SD-Tool |
| Host Parties |
Philippines
, involved indirectly
approval (98 KB)
authorization (98 KB)
Authorized Participants: First Gen Hydro Power Corporation (FGHPC) |
| Other Parties Involved | n/a |
| Sectoral scopes | 1 : Energy industries (renewable - / non-renewable sources) |
| Activity Scale | LARGE |
| Methodologies Used |
ACM0002 ver. 12 -
Consolidated baseline methodology for grid-connected electricity generation from renewable sources
|
| Standardized baselines used | N/A |
| Amount of Reductions | 29,104 metric tonnes CO2 equivalent per annum |
| Fee level | USD 4320.8 |
| Validation Report |
VVS/VVM version:
VVM 1.2
Validation report (1503 KB)
Public availability information
Link to information uploaded for public availability |
| Modalities of Communication |
MoC Annex 1 Modalities of Communication valid as of 02/05/2013 |
| Registration Date | 30 Oct 12 (Date of registration action 23 Jan 13) (view history) completeness check: complete info & rep check: concluded |
| Crediting Period |
30 Oct 12 - 29 Oct 19
(Renewable - Expired)
Renewal no longer possible
|
| Requests for Issuance
and related documentation |
|

project design document
Appendix 1 - 6782- 5_Attachment_3A_Calculation_and_Comparison_of_Financial_Indicator_as_of_18June2012_cleaned_as_of_20july_1-NWIE5B_CC- 2012 07 23
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: